Project management portal · Last updated: May 2026 · All amounts in CAD
⚙ Pending database updates
Two SQL scripts need to be run in the D1 console (Cloudflare → Workers & Pages → cafe-chouchou-db → Console):
schema-tasks-update.sql — English task content + substeps (Blocks A+B)
schema-timeline-compression.sql — 3 new tasks + 11 updates (timeline compression)
schema-tasks-update.sql — English task content + substeps (Blocks A+B)
schema-timeline-compression.sql — 3 new tasks + 11 updates (timeline compression)
$235K
Target financing
~32 wks
Timeline (compressed)
67
Planned tasks
4
Critical risks
🧭 Key decisions — session log
✓ Founders: Camila = primary founder & Futurpreneur applicant. Alex = co-founder (Cirque du Soleil background).
✓ Funding: $235K total · Fonds Jeunes Entreprises (not Entrepreneurship Fund) · ⚠ restaurant classification to confirm at PME MTL.
✓ Zones: 5 zones: L'Épicerie · La Clinique · Le Garage · Zone Active (NEW) · Espace Tout Doux. Age range 0–8.
✓ Timeline: Compressed to ~32 wks. Pre-lease work front-loaded. Target: 3–4 months lease-to-open. Free rent 2–3 months to negotiate.
✓ Memberships: Founding tiers: 1/3/6/12 months ($119→$89/mo). Unlimited = booking-required. 40% slots held for drop-ins.
✓ Infrastructure: Portal → portail.cafechouchou.ca · Public site → cafechouchou.ca · Run SQL scripts above first.
Project tools
Gantt / CPM
67 tasks, critical path, dependencies
WBS + Specs
3-level breakdown with specifications
Logic Network
PDM/CPM — ES/EF/LS/LF nodes
Action Plan
63 tasks, 3 phases, auto-save
Risk Analysis
18 risks — probability, impact, mitigations
Documents
Business plan, bid packages & more
Urgent actions — Phase 1 → full plan
Loading...
Financing tracker (click to update)
Confirmed—
Target total
$235,000
Project phases
Phase 1 — Before PME MTL
Now · 4 to 6 weeks
Phase 2 — After PME MTL
Weeks 5 to 12
Phase 3 — After lease
Financing · RBQ permit (8 wks)
Phase 4 — Construction
~20 weeks · 5 carpentry lots
Grand Opening ★
Fall 2027 (target)
Priority risks
R01 Founder capacity
R04 Summer seasonality
R05 Construction costs
R03 Multi-source financing
R09 Equipment insurance
✎ Edit Tasks
All task data is saved directly to the database — changes appear live in the Gantt and WBS
| ID | WBS | Task name | Phase | Duration | Cost range (CAD) | Status | |
|---|---|---|---|---|---|---|---|
| Loading… | |||||||
📁 Documents
Project files — download, manage and add external links
| Document | Type | Size | Actions |
|---|---|---|---|
| Loading... | |||
Upload a file
📂 Click to browse or drag & drop
PDF, Word, Excel, PowerPoint · Max 4 MB
Or add an external link
👥 Key Contacts
Advisors, lenders, regulators and service providers